Simon Sez IT

Online software training and video tutorials for Microsoft, Adobe & more

  • Course List
    • Adobe
      • Dreamweaver
        • Dreamweaver CC
        • Dreamweaver CS6
        • Dreamweaver CS5
        • Dreamweaver CS4
      • Flash
        • Flash CS5
      • InDesign
        • InDesign CS6
        • InDesign CS5
      • Photoshop
        • Photoshop CS6
        • Photoshop CS5
        • Adobe Photoshop CS4
      • Photoshop Elements
        • Photoshop Elements 2022
        • Photoshop Elements 2019
        • Photoshop Elements 2018
        • Photoshop Elements 15
        • Photoshop Elements 14
        • Photoshop Elements 13
        • Photoshop Elements 12
        • Photoshop Elements 11
        • Photoshop Elements 10
        • Photoshop Elements 9
        • Photoshop Elements 8
    • Microsoft
      • Access
        • Access 2019
        • Access 2019 Advanced
        • Access 2016
        • Access 2016 Advanced
        • Access 2013
        • Access 2013 Advanced
        • Access 2010
        • Access 2010 Advanced
        • Access 2007
      • Excel
        • Excel 2021 Advanced
        • Excel 2021 Intermediate
        • Excel 2021 Beginners
        • PivotTables for Beginners
        • Excel Dashboards
        • Advanced Formulas in Excel
        • Excel for Business Analysts
        • Advanced PivotTables
        • Power Pivot, Power Query and DAX in Excel
        • Excel 2019 Beginners (Mac)
        • Excel 2019 Beginners
        • Excel 2019 Advanced
        • Excel 2016 Beginners
        • Excel 2016 Intermediate
        • Excel 2016 Advanced
        • Excel 2013
        • Excel 2013 Advanced
        • Excel 2010 Beginners
        • Excel 2010 Advanced
        • Excel 2007
      • OneNote
        • OneNote Desktop and Windows 10
        • OneNote 2016
      • Outlook
        • Outlook 2019
        • Outlook 2016
        • Outlook 2013
        • Outlook 2010
        • Outlook 2007
      • Power Automate
        • Introduction to Power Automate
      • PowerPoint
        • PowerPoint 2021
        • PowerPoint 2019
        • PowerPoint 2016
        • PowerPoint 2013
        • PowerPoint 2010
        • PowerPoint 2007
      • Project
        • Project 2019
        • Project 2019 Advanced
        • Project 2016
        • Project 2016 Advanced
        • Project 2013
        • Project 2013 Advanced
        • Project 2010
        • Project 2010 Advanced
      • Publisher
        • Publisher 2013
      • SharePoint
        • SharePoint Online
        • SharePoint Foundation 2013
        • SharePoint Server 2013
        • SharePoint Foundation 2010
      • Teams
        • Microsoft Teams
      • VBA
        • Macros and VBA for Beginners
        • VBA for Excel
        • VBA Intermediate Training
      • Visio
        • Microsoft Visio 2019
        • Visio 2016
        • Visio 2013
        • Microsoft Visio 2010
      • Windows
        • Windows 11
        • Windows 10 (2020 Update)
        • Windows 10
        • Windows 8
        • Windows 7
        • Windows Vista
      • Word
        • Word 2019 Advanced
        • Word 2019
        • Word 2016
        • Word 2013
        • Word 2010
        • Word 2007
    • QuickBooks
      • QuickBooks
        • QuickBooks Pro 2021
        • QuickBooks Online Advanced
        • QuickBooks Online
        • QuickBooks Canada
        • QuickBooks Pro 2020
        • QuickBooks 2019
        • QuickBooks 2018
        • QuickBooks Pro 2017
        • QuickBooks Pro 2016
        • QuickBooks Pro 2015
        • QuickBooks Pro 2014
        • QuickBooks Pro 2013
        • QuickBooks Pro 2012
        • QuickBooks Pro 2011
        • QuickBooks Pro 2010
        • QuickBooks Pro 2009
    • Web Development
      • AngularJs
        • AngularJS Crash Course
      • Dreamweaver
        • Dreamweaver CC
        • Dreamweaver CS6
        • Dreamweaver CS5
        • Dreamweaver CS4
      • Bootstrap
        • Bootstrap Framework
      • Html/CSS
        • HTML/CSS Crash Course
        • HTML5 Essentials
      • Python
        • Introduction to Python
      • Java
        • Java for Beginners
      • JavaScript
        • JavaScript for Beginners
        • jQuery Crash Course
      • MySql
        • MySQL for Beginners
      • PHP
        • PHP for Beginners
        • Advanced PHP Programming
      • XML
        • XML Crash Course
    • Data Analysis
      • Financial Modeling
        • Financial Forecasting and Modeling
      • Alteryx
        • Introduction to Alteryx
      • Power BI
        • Power BI – Beyond the Basics
        • Power BI
      • Qlik Sense
        • Qlik Sense
      • R Programming
        • R Programming
      • Tableau
        • Tableau Desktop
      • Python
        • Introduction to Python
    • Work Productivity
      • Google Sheets
        • Google Sheets for Beginners
      • Confluence
        • Introduction to Confluence
      • Monday
        • Getting Started in Monday.com
      • Asana
        • Introduction to Asana
      • Jira
        • Getting Started in Jira
  • For Business
  • About Us
    • Testimonials
    • Contact Us
    • FAQ
    • Membership
    • About Us
  • Pricing
  • Free Resources
  • Sign In
  • Sign Up
Home > Microsoft Project > How to Add Resources to Tasks in Microsoft Project 2016

How to Add Resources to Tasks in Microsoft Project 2016

During this Microsoft Project 2016 training tutorial video, we will show you the different types of tasks that are available in Project 2016. Other points discussed include available options when adding resources to a task. These options are “reduce duration but keep the same amount of work,” “increase the amount of work but keep the same duration,” and “reduce the hours resources work per day (units), but keep the same duration and work.”

Facebook Linkedin Twitter

Like what you see? Get our complete Microsoft Project 2016 video training course. Click here to learn more. >>

Hello again and welcome back to our course on Project 2016.

Now that you know how to assign resources to tasks the next thing we need to move on to is producing a workable schedule given the resources that are available. In order to do that there are a couple of fundamental things that you need to understand. And perhaps the most important thing to understand with Project 2016 is the different task types that can be involved in projects.

Now in order to illustrate this I’m using a sort of dummy project, just a very simple project with three tasks in it, A, B, and C. Currently they’re each two day tasks and a resource, Jane, is working on those tasks. And Jane is working for eight hours a day. So on task A Jane is doing 16 hours work, task B 16 hours work, C 16 hours work and so on.

Now let’s suppose that I provide Jane with some help. I say, “Jane, John is going to help you.” If I assign John to task A what do you think would happen? Now what may happen is you may look at it and say well obviously Jane is going to be able to get that job done in half the time. So instead of being a two day task it’s going to be a one day task. And obviously that is one option. But there are a couple of other options as well.

One other option is that if John works on that task as well it will still take two days but they will do 32 hours work during that time. So with twice as much resource twice as much work gets done but in the same time.

Another possibility is that we still want to get our 16 hours of work done and we still want to do it in two days but the fact that we’ve got both Jane and John working on it means that they only each need to devote half their time to it. So we effectively have three options. And those three options correspond to the three options you saw in the previous section when Project 2016 said you’ve changed information about resourcing on a task.

Which of these three options would you like to use when you apply that additional resource?

Free Microsoft Project 2016 Training. Master Your Projects On Time & Budget. Click Here to Get Started.

Now let me just show you that again. I’m going to now right click on task A. I’m going to click on Assign Resources. I’m going to choose John and I’m going to say Assign. Now notice the little warning sign on the left there. Now note that Project has assumed that in assigning John I still want to spend two days on this task but by having that second person we’re getting twice as much work done. So let’s go over to that warning sign, click on the dropdown.

The default option there, the middle one, Increase the amount of work but keep the same duration. The first one was, Reduce the duration but keep the same amount of work. So in that case we would have said well we’re still going to do 16 hours work but because we’ve got two people on it we can do it in a day. The third option, Reduce the hours resources worked per day, the units, but keep the same duration and work.

So we say it’s still a two day task. It’s still only going to be 16 hours work but Jane and John only need to work half the time each.

Now let me stick with the default option and what I want to do now is to show you why that was the default option. Let me open up task A. Now the reason that was the default option was because the task type was declared as fixed duration. And very importantly the box to the right of that, Effort driven, was not checked. So what this says is this task is a fixed duration task. It’s a two day task.

And putting more effort on it will not automatically reduce its duration. So my default is to keep the duration fixed and therefore if I add resource to it I’ll just get more work done. Let me now look at task B.

Now the way that task B is set up is as a fixed work task. So the amount of work is fixed. And all fixed work tasks are effort driven. Note that the Effort driven box is checked but it’s grayed out so I can’t change it. Now what do you think will happen if I add an additional resource to this task? It’s fixed work. It’s effort driven. I’m going to assign John to it. Look what happens.

I still get 16 hours work done but of course now with the additional resource it can be done in one day. If I go over to the warning on the left and click on the dropdown the default now, Reduce the duration but keep the same amount of work. Well that is the default for a fixed work task which is always effort driven.

But I could say, Increase the amount of work but keep the same duration. So I could say well okay it’s declared to be a fixed work task but on this occasion I want to actually increase the amount of work, having put the additional resource on. And then I also have the option of reducing the hours resource work per day. So I could say okay I’ll put a second person on it. It’s fixed work.

But because I’m not changing the amount of work each of the resources only needs to work part-time on it to achieve that amount of work. Now on this occasion I’m going to stick with the default and the duration of that task has been reduced by one day.

Now let’s look at task C which is a fixed unit task and currently it’s not effort driven. Now the significance of the effort driven part is whether in fact what we’re trying to do is to do a certain amount of work, to put in a certain amount of effort. And in doing that we are flexing, we’re varying the number of people working on it or the duration in order to get that amount done. If a task is not effort driven then we’re not trying to achieve that certain amount of work, put in that certain amount of effort.

And if I put more resources on to a task then all that will happen is that more work gets done. And as a task that’s not effort driven if I assign additional resource, let’s go to town this time. Let’s assign three more resources. What is going to happen is I assign a total of four people is that we’re just getting a lot more work done on that task. Now as usual you’ve got the warning sign on the left there and you can choose a different option. But basically we’re getting the default which is, Increase the amount of work but keep the same duration.

Now let me undo that particular change. Let’s go back in now and make it an effort driven task. Now that means we’re trying to achieve a certain amount of work, putting in a certain amount of effort. Now what happens if I assign those three extra resources? Given that it’s fixed units what do you think it’s going to happen? Well what happens is that the duration is reduced. So in half a day four people can do that amount of work.

Once again of course I can go to the warning sign and change that if I want to. But basically as it’s not fixed duration putting on that extra number of people means that I can get the work done much more quickly.

As I mentioned towards the beginning of this section we’re going to be doing quite a lot on scheduling from now on. And scheduling in Project 2016 can be quite complex at times and requires quite a bit of understanding of what’s going on. There is a very useful Help article, How Project schedules tasks behind the scenes, and it’s well worth you going through this Help article. It’s very useful, very well set out. It gives a lot of very useful information.

Of course I will be covering virtually all of this on the course and quite often in a little more detail than you’ve got here. But there is a section there, I think it’s the fourth one in the list, How do task types affect the schedule, and it sets out for the different task types, fixed units, fixed work, fixed duration, what will happen if you revise units, if you revise duration, if you revise work.

Free Microsoft Project 2016 Training. Master Your Projects On Time & Budget. Click Here to Get Started.

And then gives one or two really good examples of what happens in different situations. So I do suggest that you take some time to go through this and it will really help you if you can increase the level of your knowledge on scheduling in Project 2016.

And another important point here and I briefly mentioned this right near the beginning of the course. In Project Options on the Schedule page there are a couple of very important settings. One of them is the default task type. Mine is set to fixed units. I find that that isn’t something that I leave set the same way all the time. I often vary this depending on the type of project that I’m planning.

Sometimes setting it to fixed duration or fixed work throughout the time that I’m working on a new project in particular can actually save me time. But I’ve got it set here to fixed units. And the other default here is New tasks are effort driven. In my case that is not checked. You may find that you prefer your new task to be effort driven or again you might vary it from job to job.

So that’s it. We’ve covered the basics of task types. In the next section we’re going to start to look at scheduling itself so please join me for that.

Simon Calder

Chris “Simon” Calder was working as a Project Manager in IT for one of Los Angeles’ most prestigious cultural institutions, LACMA. He taught himself to use Microsoft Project from a giant textbook and hated every moment of it. Online learning was in its infancy then, but he spotted an opportunity and made an online MS Project course - the rest, as they say, is history!

30 day vertical banner

Most Popular Posts

  • How to Insert a Checkbox in Excel? 3 EASY Examples
  • How to Autofit Excel Cells? 3 Best Methods
  • XLOOKUP Google Sheets – 4 Best Alternatives!
  • Dashboards in Excel Using Pivot Tables, Pivot Charts and Slicers
  • Free Microsoft Project Training Course
  • Free Microsoft Access Tutorial for Beginners (3.5 Hours Video)
  • How to Use Blending Mode With Layers in Adobe Photoshop Elements 15
  • How to Create Charts and Graphs in Microsoft Excel 2016

START LEARNING How to Add Resources to Tasks in Microsoft Project 2016 ON SIMONSEZIT.COM

START MY MEMBERSHIP

Similar Posts

Using SmartArt in PowerPoint 2010

How to use Statistical Functions in Excel 2013

How to Mail Merge in Word

How to Convert PDF to Word

How to Use Photoshop CS6 ? 5 Best Tips for First Time Users

How to Create Pivot Tables in Microsoft Excel 2013 – Part 1

Course Categories

  • Web Development
  • QuickBooks
  • Microsoft
  • Adobe
  • Data Analysis

About Us

  • About Us
  • Free Resources
  • Affiliates
  • Become an Instructor

Products

  • Pricing and Plans
  • Business Pricing
  • Government Discounts
  • Non-Profit Discounts

Support

  • FAQ’s
  • Contact Us
  • DVD support

Connect

YoutubeFacebook
© 2022 Simon Sez IT, Inc.
  • Terms
  • Privacy Policy
888.817.6665 Monday thru Friday 7:30 a.m. - 5:00 p.m. (ET)